Wireless Area Controllers (WACs) have been installed in a centralized location of the controlled area and are powered.
WaveLinx Area Controllers (WAHs) have been installed, are powered via POE, and are terminated properly.
All WaveLinx CAT Control Devices have been installed, labeled, are powered, and have been tested and terminated properly.
All areas / fixtures required for dimming have been wired and tested.
All ELV / MLV fixtures have the appropriate dimming module installed for 0-10v conversion.
All fixtures in daylight zones are separated and wired for individual control and are dimming as required.
All occupancy sensors are installed and are a minimum of 4-6’ away from air supply vents.
All dual-tech occupancy sensors are installed and wired to the contact closure switchpack, are a minimum of 4-6’ away from air supply vents, and have timeouts adjusted per plan requirements.
All exterior photocells are installed facing North and wired to the contact closure switchpack.
All ethernet cables have been installed and tested.
All network devices have been installed and are powered.
IT personnel have provided necessary networking information for all system devices.
All system integration devices are installed, powered and connected to the network.
Integration personnel have provided necessary information for all system devices.
Any alterations to the Lighting Control plans have been documented in a project as-built, to be provided at startup and to the client at owners training.
All device install locations have been recorded for ease of future troubleshooting and maintenance.
Sequence of operations, schedules, and business hours will be provided at time of startup.